Excavation Calculator
Work out the dirt in a pit, round hole or trench, how much it swells once dug, and how many truckloads it takes to haul.
Result
Bank volume, in the ground: 66.67 yd³
Nothing is added. Swell already covers the growth of the soil once it is out of the ground.
- Loose volume to haul
- 66.67 yd³ (1,800 ft³)Estimate
- Compacted volume as fill
- 66.67 yd³ (1,800 ft³)Estimate
https://calcgallery.com/area-volume/excavation-calculator/
Results are estimates for planning only. Actual needs vary with site conditions, products and workmanship. Always confirm quantities with your supplier and follow local building codes and manufacturer instructions. Read the full disclaimer
How to use the Excavation Calculator
- Pick a rectangular pit, a round hole or a trench, and enter its size at the bottom.
- Enter the depth, and a side slope if the sides lean outward.
- Enter the swell and shrink for your soil, from your excavator or soil report.
- Add a truck capacity to see how many loads it takes to haul the soil away.
How the volume is worked out
Sizes are taken at the bottom of the dig, and the sides lean outward from there:
Rectangle V = depth ÷ 6 × (bottom area + 4 × middle area + top area)Circle V = π × depth ÷ 3 × (r² + r × R + R²)Trench V = length × depth × (width + slope × depth)
A pit with leaning sides is not a simple box, so it uses the prismoidal rule, which is exact for this shape. With a slope of zero all three reduce to area times depth.
Why three volumes
You pay to haul loose soil and you fill with compacted soil, and neither equals the hole. A dig that leaves 80 cubic yards in trucks may only fill 60 once it is compacted back, so never order fill or trucks from the bank figure alone.
Before you dig
Call your local utility locating service first. Check whether your dig needs a permit, and treat any trench as a hazard: local rules set when sides must be sloped or shored.
With your numbers
- Loose = bank × (1 + 25%) = 83.33 yd³
- Compacted = bank × (1 − 10%) = 60 yd³
- Loads = loose ÷ 10 yd³ per truck, rounded up to 9
- Bank volume for this shape and depth = 66.67 yd³
Quick reference
Nothing is added. Swell already covers the growth of the soil once it is out of the ground.
| Job | Bank volume, in the ground |
|---|---|
| 30 × 20 ft basement, 3 ft deep | 66.67 yd³ |
| 24 × 24 ft garage pad, 1 ft deep | 21.33 yd³ |
| 50 ft trench, 2 ft wide, 4 ft deep | 14.81 yd³ |
| 10 ft round pond, 2 ft deep, 1:1 sides | 8.46 yd³ |
| 10 × 10 ft pit, 2 ft deep, 1:1 sides | 10.77 yd³ |
| 9 × 6 m pit, 1 m deep | 54 m³ |
| 20 m trench, 0.6 m wide, 1.2 m deep | 14.4 m³ |
Common questions about the Excavation Calculator
- What is the difference between bank, loose and compacted volume?
- Bank volume is the soil as it sits in the ground. Loose is the same soil after digging, which takes up more room in a truck. Compacted is what it fills once rolled or tamped back down.
- How many truckloads is a 30 by 20 ft dig, 3 ft deep?
- That is 66.67 cubic yards in the ground. With 25% swell it hauls as 83.33 cubic yards, which is 9 loads in a 10 cubic yard truck.
- Why does this ask me for swell instead of giving one?
- Swell changes with the soil and how wet it is. Clay, sand and rock differ widely, so the number should come from someone who has seen your site.
- Does this tell me how steep my trench sides can be?
- No. Safe side slopes and shoring depend on soil and depth and are set by local rules. Trench collapse is a serious hazard, so get that decision from a competent person.